Bishalgarh Central Prison construction multi-crore scam : PWD Executive Engineer, Party leaders, Kolkata based Engineering Projects India Ltd embezzled crores
TIWN
Bishalgarh Central Prison construction multi-crore scam : PWD Executive Engineer, Party leaders, Kolkata based  Engineering Projects India Ltd  embezzled crores
PHOTO : Central Prison, Bisalgarh. TIWN File Photo

AGARTALA, December 7 (TIWN): Fraudulent manipulations by corrupt officials in PWD, Executive engineer's office, Kolkata based Engineering Projects India Ltd on Bisalgarh Central Prison construction project resulted over Rs. 5 crores funds misappropriation. The Home (Jail) Department accorded (December 2007) administrative approval for Rs. 62.55 crore and expenditure sanction of ` 15.00 crore for construction of 1000 intake capacity Model Central Prison at Bishalgarh. The work was awarded (October 2007) on turnkey basis to the lowest tenderer, M/s Engineering Projects India Ltd (EPIL), Kolkata, with the approval (October 2007) of the Work Advisory Board at the negotiated value of ` 62.55 crore with the stipulation to complete the work within two years. However corrupt nexus among PWD EE, Party leaders and EPIL caused multi-crore embezzlement of funds in Central Prison construction, project funding was provided from Modernisation Scheme and TFC grants.Bishalgarh Central Prison construction CAG reports clearly pinpoints funds misappropriation.

1. Rs. 1.01 crore expenditure was shown on paper as “infructuos expenditure” due to Faulty planning and arbitrary decision to abandon the work after completing upto plinth level for “Construction of Recreation Hall cum Library for Cultural Activities” at Central Prison. But fact is no proof exists and this Rs.1.01 crore was siphoned off by corrupt officials.

2. Rs. 1.56 crore extra fake expenditure was shown in paper but no proof exists – this Rs. 1,56 crore was siphoned off by PWD EE and EPIL Kolkata in complete violation of the contractual provisions under turnkey contract for construction of the Central Prison at Bishalgarh, payment by the Department towards land/site development as an additional item, which fell well within the scope of work of turnkey contract. This rendered the expenditure of ` 1.56 crore extra, of which had been paid to M/s Engineering Projects India Ltd.

3. Rs. 2.51 crores fake expenditure was shown as land development, project delay costs in construction of various buildings, structures, perimeter walls, etc. of the Central Prison at Bishalgarh, payment by the Department towards land/site development as additional item.  

CAG report says,”In violation of the contractual provisions under turnkey contract for construction of the Central Prison at Bishalgarh, payment by the Department towards land/site development as an additional item, which fell well within the scope of work of turnkey contract. This rendered the expenditure of ` 1.56 crore extra which is paid to M/s Engineering Projects India Ltd”.

With the approval (October 2007) of the Works Advisory Board (WAB), the work “Planning, designing, detailed engineering and execution of Central Prison at Bishalgarh was awarded on turnkey basis to the lowest tenderer25, M/s Engineering Projects India Ltd (EPIL), Kolkata at the negotiated value of ` 62.55 crore with the stipulation to complete the work within 24 months. The work commenced in November 2008 and was in progress (June 2013). Against the value of work done (` 55.92 crore) EPIL was paid (July 2013) ` 53.83 crore (upto 61st RA bill). 
It was however, seen that against land/site development works (as additional item) the EE had paid EPIL (at provisional rates subject to approval of higher authority) ` 62.58 lakh in February 2012 (44th RA bill) and ` 3.54 lakh in June 2012 (45th RA bill), which was beyond the terms of the turnkey contract. It was further observed that as per decision of the Chief Engineer, PWD (R&B), the EE asked EPIL (July 2012) to take up all the additional works for which payment would be made on the basis of TSR 2008 adding 40 per cent cost enhancement charge.
Thereafter EPIL was paid ` 11.01 lakh in August 2012 (50th RA bill) and ` 7.27 lakh in July 2013 (61st RA bill). Against total value of work done for ` 1.56 crore (upto 9th RA bill) as additional item towards area development by cutting/ transportation/filling of earth EPIL was paid ` 84.40 lakh  (upto 61st RA bill) for which no justification was available". This whole Rs. 1.56 expenditure is bogus.
 
"As per the terms and conditions, the required quantity of excavated earth would be stacked in the nearby area for back filling the same after casting of the structure was completed and the surplus excavated earth would be loaded manually/mechanically into tippers and disposed in the designated places.
"Thus, in violation of the contractual provisions under turnkey contract for construction of various buildings, structures, perimeter walls, etc. of the Central Prison at Bishalgarh, payment by the Department towards land/site development as additional item, which fell well within the scope of work of turnkey contract rendered".

Embezzlement is an art perfected by Tripura's "Mr Clean" and his competent close aides like BDO Bimal Chakraborty. 
 
 
 
 