TIWN August 10, 2016
AGARTALA, Aug 10 (TIWN): During the Budget counter speech held on June 30, AMC Mayor Prafullajit Sinha placed vivid explanation about the expenditure from 2015 to 2016 and also placed the budget for the year 2016-17. During the budget counter speech he talked about various projects ongoing and also completed project among which Mayor claimed about the almost completion of JNNURM’s (Jawharlal Nehru Urban Development Mission) Rs. 102.22 crores, which was sanctioned for Storm Water Drainage system.
But in reality there is no sign of proper drainage yet arranged in Agartala city. With a few splash of rain the city dupes into water and water logging till waist, is very common for Agartala City.
Whereas West Bengal, Andra Pradesh, Gujrat, Maharasthra have completed the project long back in the year 2012, Tripura is suffering from water logging condition after every rain-splash. But surprisingly, in AMC Budget it has been shown that in the year 2015-16 the work has been completed almost.
As per the central provided project, the major components of the project includes construction of storm Water Drainage system consisting of construction of brick masonry surface drains with desalting of the existing outfall. After implementation of this project the aim was removal of water logged areas during monsoon season but Agartala City’s condition has been remained as it is.
Heavy monsoon rainfall in Agartala resulted in water logging in the city, cause a lot of problems to the locals. Reportedly, there are 8 – 10 points in the city where water-logging are a perennial problem during monsoon, triggering severe traffic jams and flooding in various localities. Drain-water and rainwater flushes the households.
Thus it will be worthy mention here that whereas on the one hand Modi govt. trying to upgrade the city into a SMART City, on the other hand, the water-log problem battles with Modi’s SMART City vision.
The water logging problem of Agartala seems unending as AMC failed to bring out 1 percent of solution to the water log problem here, but still in budget it has been shown that the work is almost completed.
- Storm, Hailstorm dismantled home : Family forced to survive under Open-Sky with Children : Seek Govt assistance
- Human Trafficking : 2 more arrested by GRP Police
- ‘The Real Culprits will never be Arrested ; Only some people made Scapegoats’: Sudip Barman’s blasted on BJP Govt over Vicky murder case investigation
- Huge Quantities of Expired Chips, Cold Drinks Seized from Tripura University lined Shops
- 23 years girl arrested in Bharat Ratna Club Secretary Vicky murder case