AGARTALA, May 21 (TIWN): In a fresh initiative to present Tripura in the front figure of the world, NFR Railway planning to open a new railway division based at Tripura. But still now confusion brewing about choosing the right place in Silchar (Assam) or Tripura. It is to be mentioned that broad gauge line was already started Lumbding-Silchar Route. According to NF Railway authorities, by 2016, it would extend further to Agartala and within March 2016, Udaipur to be on Railway map. Further broadgage line will connect Sabroom within two years. The supporters who are in favour of Tripura made statement that; it is not possible to operate both Agartala and Silchar from Lumbding division. Still now there are five railway divisions- 3 are at Assam, others are at Bihar and West Bengal.The authorities of Maligaon Railway division told that for the construction of railway division, minimum four hundred and half or 500 hectares of land is required which is essential to build the office of the General Manger, controlling room , staff headquarter and other essential things.The BG conversion work from Karimganj to Agartala likely to start from October 1. Earlier, the first broad-gauge engine had knocked the door of the people of Silchar on March 13. commissioning of laying and constructing of Broad Gauge (BG) railway tracks of Mega Block for Agartala to Sabroom will start from March 2018.
Cconversion work from Badarpur to Agartala has already been started and is likely to be completed in March next year. Conversion work of 108 kilometer railway tracks of Mega Block has been already completed out of 228 kilometers.
The work of 44 locations out of 102 was over by now, with achieved connectivity between Mandardisa to Hatikhali on October 26. The longest tunnel measuring length of 3.235 kilometres was successfully completed with new railway tracks of Broad Gauge was Tunnel No. 10. About 3000 numbers of track linking and other labour has been mobilized by various agencies working in the section. However, question could be raised on sanctioning of fund for Metre Gauge (MG) prior to it on 2008/09 Financial Year, on why government has accepted on this pact then, if the Centre had different plans to lay BG connection in state’s railway.
This is a jargon for many citizens transporting in the state due to a halt in railway connectivity in between on which depended livelihoods of a chunk of populace in Tripura’s railway stations. However, the speedy work construction has kept the dreams alive for many with altogether 17 tunnels’ work get is expected to be over by January next year. Tunnel No.11 has been made through on October 13 and ROB no. 84 has been commissioned on October 20 and this will enable completion of yard works at Jatinga Lumpur station. Seven lac cum of earthwork has since been done during mega block out of 12 lac cum. Track linking of BG line is also progressing satisfactorily at various locations.
- 3 arrested from Ramnagar HC Staff Quarter with Drugs
- Massive traffic Jams in Agartala as Auto Drivers Blocked Drop Gate National Highway protesting against CNG Crisis
- Storm, Hailstorm dismantled home : Family forced to survive under Open-Sky with Children : Seek Govt assistance
- Human Trafficking : 2 more arrested by GRP Police
- ‘The Real Culprits will never be Arrested ; Only some people made Scapegoats’: Sudip Barman’s blasted on BJP Govt over Vicky murder case investigation